Challenge
A drilling team needed to capture daily mud properties during operations, but the workflow was inefficient and error-prone. Mud engineers submitted spreadsheets that supervisors manually re-entered into WellView Allez, taking up to 30 minutes per report. Across a multi-week drilling program, this resulted in hours of repetitive entry, frequent rework, and limited ability to analyze or benchmark performance.
Solution
The team implemented a vendor-neutral WITSML loader mapped directly to WellView Allez’s data model. Vendors submitted data in a standardized format, which could be imported with a single click. Input time dropped from 30 minutes to seconds, and manual re-keying was eliminated. Field teams focused on validating data quality rather than re-entering it, enabling faster operational insights and more reliable drilling data management.